CONSTRUCTION WORK TASKS DURATION: NEW METHOD OF ESTIMATION AND QUALITY CONTROL


DOI: 10.5937/jaes14-10443
This is an open access article distributed under the CC BY-NC-ND 4.0 terms and conditions. 
Creative Commons License

Volume 14 article 362 pages: 121-127

Sergei Bovteev
St. Petersburg State Polytechnical University, Saint-Petersburg, Russia

Svetlana Kanyukova
St. Petersburg State Polytechnical University, Saint-Petersburg, Russia

Vladimir Okrepilov
State Regional Centre for Standardization, Metrology and Testing in St. Petersburg and Leningrad Region (State Centre “Test-St. Petersburg”), St. Petersburg, Russia

Anna Rezvaia
Magadan Institute of Economics , Saint Petersburg, Russia

The article considers the principles of ensuring the completion of construction projects to meet the date. The authors suggest the method of assessing the progress of the project and estimating timely completion of the project based on the application of the Schedule Timeless Index (STI) and the Schedule Progress Index (SPI). The method allows to analyze dynamically the deviation of the timing of the project for prompt adoption of effective management decisions.

View article

Archibald, R.D. (2003): Managing High-Technology Programs and Projects, 3rd Edition p. 396.

Bovteev, S., Terentieva, E. (2014): Construction project schedule control, Projectand Program Management, No.2, pp. 158-173.

Cetkovic J., Rutesic S., Zarkovic M., Knezevic M., Vatin  N.  (2015):  Primary  directions  and advancements  in  competitiveness  of  montenegrin construction sector, Procedia Engineering, 117 (1), pp. 780-790.

Cetkovic,  J.,  Knezevic,  M.,  Zarkovic,  M., Murgul, V., Vatin, N. Development and competitiveness  improvement  of  the  construction  sector  in  Montenegro  (2014)  Applied Mechanics and Materials, Vols. 638-640, pp. 2465-2470.

Chatfield,  C.,  Johnson,  T.  (2013):  Microsoft  Project  2013.  Step  by  step,  Redmond, Washington.

Chegotova, E.V. (2012): The Role of technical  customer  in  the  organization  of  investment activities  in  construction, Magazine of Civil Engineering, 29(3), pp. 5-11.

Heldman, K. (2009): PMP: Project Management  Professional  Exam  study  Guide,  5th Edition, p. 677.

Homutinnikova, K. C. (2009): Evaluation Criteria methods of verification used in managing construction projects, Management projects and programs, No.4, pp. 312-323.

ICB-IPMA  Competence  Baseline  (2006): Version 3.0. Nijkerk, The Netherlands.

L.Lynch. (2010): On Time and under budget: a project management method critical chain (2010) pp. 354.

Project  Management  Body  of  Knowledge (2012):  5th  ed.  Project  Management  Institute. Newtown Square, Pennsylvania.

Project Management in Construction. Fourth Edition. pp. 285.

Ptukhina,  I.S.  (2011):  Methodology  of  the distribution of economic justice the perpetrators for the delay of completion, Kuban state agrarian University, 04(68), pp. 383-394.

Pukhkal, V., Murgul, V., Garifullin, M. (2015):Reconstruction  of  Buildings  with  a  Superstructure Mansard: Options to Reduce Energy Intensity of Buildings, Procedia Engineering, Vol. 117, pp. 624-627.

Rutesic  S.,  Cetkovic  J.,  Knezevic  M., Zarckovic  M.,  Vatin  N.  (2015):  Institutional framework,  current  investments  and  future strategic  direction  for  development  of  construction sector in Montenegro, Procedia Engineering, 117 (1), pp. 642-650.

Rutesic  S.,  Cetkovic  J.,  Zarckovic  M., Knezevic  M.,  Vatin  N.  (2015):  Analysis  of the  situation  in  montenegrin  civil  engineering sector from the point of application of national regulations and the EU technical standards in construction, Procedia Engineering, 117 (1), pp. 905-915.

Schlagbauer, D., Heck, D. (2013): Change in output performance due to prolonged work, ISEC 2013 - 7th International Structural Engineering and Construction Conference: New Developments in Structural Engineering and

Construction, pp. 1375-1380.

Suetin, S.N., Titov, S.A. (2014): Project portfolio management: strategic  level  of  project management,  Economy  and  Entrepreneurship, 5-2 (46-2), pp. 509-515.

Vatin,  N.I.,  Kolosova,  N.B.,  Berdyugin,  I.A. (2013): Efficiency of application of automatic control systems, accugrade in  construction, Construction of Unique Buildings and Structures, 4 (9), pp. 29-35.

W. Lipke. (2012): Earned schedule contribution to project management, PM World Journal, Vol. 1, Issue 2.

Werkl,  M,  Heck,  D.  (2011):  Coping  with  incompleteness: An approach using time and production  related  compensation,  ISEC

- 6th International Structural Engineering and Construction  Conference:  Modern  Methods and Advances in Structural Engineering and Construction, pp. 279-284.

Williams,  D.L.  Krazer,  E.B.  (2012):  Oracle Primavera P6 Version 8: Project and Portfolio Management: A comprehensive Guide to managing projects, resources, and portfolios using Primavera P6, through version 8.2. Birmingham & Mumbai: PACKT Publishing.

Yakovlev, Y.V. (2010): Mechanisms of management  of  complex  investment  and  construction project, Moscow: Creative house.

Yu. N. (2008): Lapygin Project management: from planning to evaluation, Moscow: Omega-L, p. 252.

Zakieva,  N.M.,  Sirazetdinov,  R.M.  (2011): Corporate  project  management  system  as management mechanism of innovative projects  in  investment-construction  complex, News of the Kazan, No.3, pp. 211-218.